Gantter™ is one of the best CPM project management tools in the Google Chrome Web Store that has all the power of leading desktop project management and project scheduling desktop software products like MS Project™ and with all the advantages of the cloud. It can even read and write MS Project™ (.MPP files).
Gantter™ was designed to provide Google™ users the most natural Google Drive Editor-like experience for their online project management needs. It is a free project management tool that offers a variety of features. Google users enjoy single sign-on, bi-directional task syncing from Gantter schedules to their Google Calendars, storing files on Google Drive™ and Google Team Drive™, collaborative real-time editing that feels like a native Google editor, integrated Google Comments, and even the ability to start a Google Hangout with team members from their Gantter™ schedule, and much more.
Navigating the Website and Signing Up

Click on the green 'Start Now' box to the right.

Look at the login screen you are directed to. Using Gantter requires you to have a SmartApp account. If you do, type in your email and password in the login form, then click on "Login".

Click on 'Register Now' at the bottom if you do not have a SmartApp account. You will need to type in your first name, last name, an email address, password, and provided CAPTCHA code. Make sure to type in a valid e-mail address, so you can confirm it once you have registered.Use Gantter to Manage Your Projects Step 3Bullet1.jpg Also, make sure to read all the Terms of Service and privacy policies. Those are the documents you will need to agree to when you register.Use Gantter to Manage Your Projects Step 3Bullet2.jpg If you do not want to register 'directly' for a SmartApp account, you can click on "Register with Google", "Register with Facebook" or "Register with Linkedin" instead. This will link your Google, Facebook or LinkedIn account to SmartApp/Gantter.Use Gantter to Manage Your Projects Step 3Bullet3.jpg

Check the email you typed in, for a confirmation email (you should either see this in your inbox or the junk mail folder). Click on the link that you are given to confirm your e-mail, so you can start using your account for project management.
Managing Your Projects

Look at the window you are taken to. The window includes the buttons "Project", "Edit", "View", "Actions", "Extensions" and "Help" at the top. You will also see the buttons "Tasks", "Resources", and "Calendars", at the near-bottom. You will also see a chart in the "file" you are editing. There are 5 fields: Name, Duration, Start, Finish, Predecessors, and Resources.Use Gantter to Manage Your Projects Step 5Bullet1.jpg

Type in the name of the project you are managing, in the "Name" field. If you are managing more than one project at once, type in the name of each project.

Manage the project resources. To do this, click on the Resources tab. Type in the name of each resource under "Resource Name". Type in the email for each resource. Choose the type of resource that each one is, from the small drop-down. It can either be "Work" or "Material". Type the cost for each resource, if any.

Click on the Calendar tab to view your calendar names. The default ones are 'Standard', '24-Hours' and 'Night Shift'. You can, however, edit those and create your own 'custom' names.